AFE No. S-1-26

Sta or MP: Millers Spur, ND

Division: Minnesota

Work Begun: Mar 19, 1926

Project Completed: May 7, 1926

Description of Project: Purchased necessary additional land and constructed 32x32 one pen addition to stock yard at Millers Spur with water service line.  AFE S-594-24 covers original pen pipelines and ROW.  Ret S-400-50

Graphic: Map

 

AFE No. S-2-26

Sta or MP: Belden, Minn

Division: TC Term

Work Begun: Sep 16, 1925

Project Completed: Sep 17, 1925

Description of Project: Installation of Henggi Rail anchors near Belden between MP 121 and MP 126.

Graphic: None

 

AFE No. S-3-26

Sta or MP: Rolette, ND

Division: Winnipeg

Work Begun: Jan 10, 1926

Project Completed: Jan 15, 1926

Description of Project:  Wired depot living rooms at Rolette for electric lights.  Labor and material furnished by agent.

Graphic: None

 

AFE No. S-4-26

Sta or MP: Hazel and Thief River Falls, Minn

Division: Winnipeg

Work Begun: Apr 1, 1926

Project Completed: Apr 2, 1926

Description of Project: Installation of telegraphone sets at Hazel and Thief River Falls for telephone communication between these towns. To enable custodian at Hazel to furnish the public info concerning train movement and etc. S-57-40.

Graphic: None

 

AFE No. S-5-26

Sta or MP: Drake, ND

Division: Minnesota

Work Begun: Feb 25, 1926

Project Completed: Feb 27, 1926

Description of Project: Installation of telephone set on pole west end of Drake yard to facilitate train work.

Graphic: None

 

AFE No. S-6-26

Sta or MP: Marblehead Spur, Mich

Division: Gdstn

Work Begun: Jun 2, 1925

Project Completed: June 2, 1925

Description of Project: Extension of 8 ft to present 16 ft highway crossing at sta 68+00 on the Marblehead Spur, track icc208, Mich trunk hwy 12.

Graphic: Map

 

AFE No. S-7-26

Sta or MP: Artas, SD

Division: Mo River

Work Begun: Aug 15, 1925

Project Completed: Aug 15, 1925

Description of Project: Placed tie rods on channel switch at Artas.

Graphic: None

 

AFE No. S-8-26

Sta or MP: Shoreham, Minn

Division: TC Term

Work Begun: Dec 20, 1924

Project Completed: Nov 17, 1925

Description of Project: Installed 578 LF of 6” tile drain from ice house, bldg 5, at Shoreham to existing manholes.

Graphic: Map

 

AFE No. S-9-26

Sta or MP: Various, Minn

Division: D&S

Work Begun: Apr 24, 1926

Project Completed: Oct 15, 1926

Description of Project: Renewed culverts at various locations with concrete pipe.  Abandoned culvert O-151-R and filled up ends.  25 culverts between MP 108 and MP 186 on Brooten Line.

Graphic: None

 

AFE No. S-10-26

Sta or MP: Various, Minn

Division: D&S

Work Begun: Apr 2, 1926

Project Completed: Mar 10, 1927

Description of Project: Abandoned and filled culverts, renewed Culverts, 20 located between MP 194 and MP 264 on Brooten Line.

Graphic: None

 

AFE No. S-11-26

Sta or MP: Various, Wis

Division: D&S

Work Begun: Mar 1926

Project Completed: Jul 23, 1926

Description of Project: Renewed portion of culvert O-279-Q under main line with concrete and salvage portion on north side of storage track account too long.  Renew culvert O-279-R with concrete pipe.  Abandon culverts O-273-1/8-P and

O-273-2/8-P.

Graphic: None

 

AFE No. S-12-26

Sta or MP: Various, Minn

Division: D&S

Work Begun: May 1926

Project Completed: Oct 12, 1926

Description of Project: Renewed 9 culverts, abandon & fill 3 culverts and one at Federal Dam on south side of track east of car house, which has no number.  13 culverts between MP 249 and Federal Dam.

Graphic: None

 

AFE No. S-13-26

Sta or MP: Cuyuna Line, Minn

Division: D&S

Work Begun: Aug 19, 1926

Project Completed: Aug 19, 1926

Description of Project: Abandoned and salvaged pipe and filled culverts at A.E.300-P-5/8 and A.E.-301-R-!/8

Graphic: None

 

AFE No. S-14-26

Sta or MP: Various, Minn

Division: D&S

Work Begun: Apr 20, 1926

Project Completed: Aug 24, 1927

Description of Project: Renewed 8 culverts between MP 340 and MP 416 and retire 5 culverts between MP 341 and MP 361.

Graphic: None

 

AFE No. S-15-26

Sta or MP: Various, Minn

Division: D&S

Work Begun: May 1926

Project Completed: Sep 4, 1926

Description of Project: Renewed 6 old worn out culverts with reinforced concrete pipe and retired 3 culverts between MP 267 and MP 303 on Cuyuna Line

Graphic: None

 

AFE No. S-16-26

Sta or MP: Various, ND

Division: Minnesota

Work Begun: Apr 2, 1926

Project Completed: Oct 30, 1926

Description of Project: Renewed old worn out timber culverts with reinforced concrete culvert pipe at 4 culverts between MP 462 and MP 527.

Graphic: None

 

AFE No. S-17-26

Sta or MP: Culvert 314-Q, ND

Division: Minnesota

Work Begun: Nov 3, 1926

Project Completed: Nov 4, 1926

Description of Project: Renewed Culvert 314-Q double 3x4-28 timber box with 28’ of 30” concrete pipe and removed old culvert.

Graphic: None

 

AFE No. S-18-26

Sta or MP: Oswald, ND

Division: Minnesota

Work Begun: Jul 10, 1926

Project Completed: May 14, 1927

Description of Project: Renewed timber bridge over highway ditch at south side of stockyard at Oswald with galvanized iron pipe and filled over pipe.  Also renewed 30’ portion of Culvert 223-Q-2/8 under highway on left with galvanized iron pipe.

Graphic: None

 

AFE No. S-19-26

Sta or MP: Eden, SD

Division: Minnesota

Work Begun: May 3, 1926

Project Completed: May 3, 1926

Description of Project: Abandon culvert Y-257-Q at sta 1090+52 near Eden.

Graphic: None

 

AFE No. S-20-26

Sta or MP: Lamars, ND

Division: Minnesota

Work Begun: Nov 16, 1926

Project Completed: Nov 17, 1926

Description of Project: Renewed Culvert Y-202-R with concrete pipe near Lamars.

Graphic: None

 

AFE No. S-21-26

Sta or MP: Various, Minn

Division: Minnesota

Work Begun: Mar 1926

Project Completed: Nov 1926

Description of Project: Renewed 4 culverts between MP 126 and MP 165.

Graphic: None

 

AFE No. S-22-26

Sta or MP: Dickinson, Minn

Division: Minnesota

Work Begun: Mar 30, 1926

Project Completed: Apr 5, 1926

Description of Project: Renewed galvanized iron pipe at Culvert 29-1/8-Q at sta 1556+87 near Dickinson under farm crossing approach on right with concrete pipe.

Graphic: None

 

AFE No. S-23-26

Sta or MP: Newfolden, Minn

Division: Winnipeg

Work Begun: Apr 26, 1926

Project Completed: Apr 26, 1926

Description of Project: Abandonment of private crossing at sta 3315+00 west of MP 327 account no longer needed.

Graphic: Map

 

AFE No. S-24-26

Sta or MP: Harlis, Minn

Division: TC Term

Work Begun: Jul 24, 1925

Project Completed: Jul 24, 1925

Description of Project: Retire section house at Harlis destr by fire Jul 24, 1925.   24x28 was installed 1912.

Graphic: Map

 

AFE No. S-25-26

Sta or MP: Minneapolis, Minn

Division: TC Term

Work Begun: Jan 1, 1926

Project Completed: Dec 31, 1926

Description of Project: Purchase of office furniture and misc office equip during year 1926 for General Office.

Graphic: None

 

AFE No. S-26-26

Sta or MP: Spur 206, Minn

Division: Winnipeg

Work Begun: Apr 29, 1926

Project Completed: May 25, 1926

Description of Project: Retirement of Spur 206 length 456 ft track icc34.  This track was partially retired by AFE S-617-25 orig length was 621 ft.

Graphic: Map

 

AFE No. S-27-26

Sta or MP: Hawkins, Wis

Division: Gdstn

Work Begun: Apr 4, 1926

Project Completed: Oct 31, 1926

Description of Project: Construction of a farm crossing at sta 8051+45 for Geo H Gerzema, one mile east of Hawkins, to be used for hauling wood.

Graphic: Map

 

AFE No. S-28-26

Sta or MP: Various, ND

Division: Winnipeg

Work Begun: Jun 1926

Project Completed: Oct 13, 1926

Description of Project: Renewed old worn out timber culverts, 4 between MP J-526 and MP J-589.

Graphic: None

 

AFE No. S-29-26

Sta or MP: Various, ND

Division: Winnipeg

Work Begun: May 14, 1926

Project Completed: Jul 8, 1926

Description of Project: Extended, renewed, repaired, and rip-rapped highway and roadway, 12 culverts between MP 411 and MP 503 on Wheatline.

Graphic: None

 

AFE No. S-30-26

Sta or MP: Various, ND

Division: Winnipeg

Work Begun: May 5, 1926

Project Completed: Nov 9, 1926

Description of Project: Renewed, extended, repaired, and rip-rapped highway and roadway, 15 culverts between MP 356 and MP 405 on Wheatline.

Graphic: None

 

AFE No. S-31-26

Sta or MP: Various, ND

Division: Winnipeg

Work Begun: Apr 29, 1926

Project Completed: Jul 12, 1926

Description of Project: Renewed old worn out timber box railway and highway culverts with reinforced concrete pipe at 4 locations MP 394 to MP 437 on Fordville-Drake Line.

Graphic: None

 

AFE No. S-32-26

Sta or MP: Various, Minn

Division: Winnipeg

Work Begun: May 6, 1926

Project Completed: May 26, 1926

Description of Project: Renewed 10 culverts between MP 313 and MP 348 on Wheatline.

Graphic: None

 

AFE No. S-33-26

Sta or MP: Various, Minn

Division: Winnipeg

Work Begun: Apr 1, 1926

Project Completed: Sep 18, 1926

Description of Project: Renewed and extended railway and highway culverts at 16 locations between MP 253 and MP 355 on G-Line.

Graphic: None

 

AFE No. S-34-26

Sta or MP: Various, Minn

Division: Winnipeg

Work Begun: Mar 27, 1926

Project Completed: Nov 16, 1926

Description of Project: Renew and extend culverts at 24 locations between MP 142 and MP 229 on G-Line.

Graphic: None

 

AFE No. S-35-26

Sta or MP: Carrington, ND

Division: Minnesota

Work Begun: Dec 7, 1925

Project Completed: Dec 8, 1925

Description of Project: Extended existing 6x35 timber curbed earth filled automobile loading platform with 6x13 and 6x6 earth filled platform at east end, to a two car capacity structure 6x75 with 6x12 end wood curbed, earth filled construction  and extend spur track 40 track feet.  Spur headblock at sta 7742+70 track icc100.

Graphic: Map

 

AFE No. S-36-26

Sta or MP: Leonard, Minn

Division: D&S

Work Begun: Jan 12, 1926

Project Completed: Jan 12, 1926

Description of Project: Constructed 16x16 timber unloading platform at Leonard opposite depot on house track to facilitate handling of farm machinery.

Graphic: Map

 

AFE No. S-37-26

Sta or MP: Superior, Wis

Division: D&S

Work Begun: May 26, 1926

Project Completed: Jun 12, 1926

Description of Project: Constructed addition to stairway and platform on north and east side of McHenry coal chute extending same to top, to avoid hazard in employees climbing structure when necessary to reach top.

Graphic: Map

 

AFE No. S-38-26

Sta or MP: Dakota Jct, Minn

Division: Winnipeg

Work Begun: Dec 17, 1925

Project Completed: Dec 17, 1925

Description of Project: Retire car body at Dakota Jct, sold to C G Nullen per auth of Gen Supt account no longer needed.

Graphic: Map

 

AFE No. S-39-26

Sta or MP: Various, Mich

Division: Gdstn

Work Begun: Jan 6, 1926

Project Completed: Jan 15, 1926

Description of Project: Construct four standard record cabinets, per plan 16555 size 6x6 at Fairthorn Jct, Hermansville, and North Escanaba.

Graphic: None

 

AFE No. S-40-26

Sta or MP: Various, Mich

Division: Gdstn

Work Begun: Jan 1, 1926

Project Completed: Jan 31, 1926

Description of Project: Construct and install 6 record cabinets and repair one at Gould City, Engadine, Gilchrist, Rexton, Rudyard, and Dafter.

Graphic: None

 

AFE No. S-41-26

Sta or MP: Various, Minn

Division: Minnesota

Work Begun: Jan 20, 1926

Project Completed: Mar 12, 1926

Description of Project: Constructed 12 standard record cabinets, per plan 16555. Located at Glenwood, Lowry, Farwell, Kensington, Hoffman, Barrett, Elbow Lake, and Wendell.

Graphic: None

 

AFE No. S-42-26

Sta or MP: Various, Minn

Division: Winnipeg

Work Begun: Jan 15, 1926

Project Completed: Mar 15, 1926

Description of Project: Construct 18 standard record cabinets, plan 16555.  At Forada, Carlos, Parkers Prairie, Ottertail, Richville, Dent, Vergas, Detroit Frt, Callaway, Ogema, Waubun, and Mahnomen.

Graphic: None

 

AFE No. S-43-26

Sta or MP: Various, Minn

Division: D&S

Work Begun: Jan 4, 1926

Project Completed: Jan 30, 1926

Description of Project: Constructed 11 standard record cabinets, plan 16555. At Kettle River, Automba, Lawler, Mcgregor, Palisade, Bain, Swatara, Shovel Lake, Remer, Boy River, and Federal Dam.

Graphic: None

 

AFE No. S-44-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Jan 4, 1926

Project Completed: Jan 20, 1926

Description of Project: Constructed 9 standard record cabinets, plan 16555.  At St Croix Falls, Centuria, Milltown, Luck, Frederic, Lewis, Siren, Webster, and Danbury.

Graphic:None

 

AFE No. S-45-26

Sta or MP: Various, ND

Division: Minnesota

Work Begun: Jan 1926

Project Completed: Apr 30, 1926

Description of Project: Constructed 5 standard record cabinets, plan 16555.  At Fairmount, Hankinson, Mantador, Wyndmere, and Anselm.

Graphic: None

 

AFE No. S-46-26

Sta or MP: Various, ND

Division: Mo River

Work Begun: Mar 1, 1926

Project Completed: Mar 26, 1926

Description of Project: Constructed 11 standard record cabinets, plan 16555.  At Geneseo, Ransom, Forman, Cogswell, Oakes, Fullerton, Merricourt, Kulm, Fredonia, Lehr, and Wishek.

Graphic: None

 

AFE No. S-47-26

Sta or MP: Various, ND

Division: Mo River

Work Begun: Nov 4, 1925

Project Completed: Jan 27, 1926

Description of Project: Equipped section tool houses with storage bins and shelves per standard plan 16994.  At Burnstad, Napoleon, Braddock East, Braddock West, Brittin, Magnus, Bismarck East, Bismarck West, and Ashley.

Graphic: None

 

AFE No. S-48-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Oct 9, 1926

Project Completed: Nov 10, 1926

Description of Project: Equipped section tool houses with storage bins and shelves per standard plan 16994.  At Barron and Turtle Lake.

Graphic: None

 

AFE No. S-49-26

Sta or MP: Various, Wis

Division: Gdstn

Work Begun: Aug 27, 1925

Project Completed: Mar 10, 1927

Description of Project: Equipped section tool houses with storage bins and shelves per standard plan 16994. At Starks, Gagen, Argonne East, Argonne West, Cavour East, Cavour West, Armstrong Creek, Goodman, Dunbar, Pembine east and Pembine West.

Graphic: None

 

AFE No. S-50-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Oct 16, 1925

Project Completed: Nov 11, 1925

Description of Project: Equipped section tool houses with storage bins and shelves per standard plan 16994.  At St Croix Falls, Centuria, Luck, Frederic, Lewis, Siren, Webster, and Danbury.

Graphic: None

 

AFE No. S-51-26

Sta or MP: Dallas, Wis

Division: TC Term

Work Begun: Oct 5, 1926

Project Completed: Oct 5, 1926

Description of Project: Equipped section tool house with storage bins and shelves per standard plan 16994 at Dallas.

Graphic: None

 

AFE No. S-52-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Nov 30, 1925

Project Completed: Apr 10, 1928

Description of Project: Equipped section tool houses with storage bins and shelves per std plan 16994. At Patzau and Black River.

Graphic: None

 

AFE No. S-53-26

Sta or MP: Various, Wis

Division: Gdstn

Work Begun: Sep 5, 1925

Project Completed: Nov 4, 1925

Description of Project: Equipped section tool houses with storage bins and shelving per std plan 16994.  At Crandon North, Crandon South, Woodlawn, Lily, Hollister, White Lake, Neopit North, Neopit South, Gresham, Shawano North, Shawano South, Navarino, Nichols, Black Creek, Appleton North, and Appleton So

Graphic: None

 

AFE No. S-54-26

Sta or MP: Various, Minn

Division: TC Term

Work Begun: Jul 17, 1925

Project Completed: Jul 1, 1926

Description of Project: Equipped section tool houses with storage bins and shelving per std plan 16994.  At Bald Eagle Jct and Maple Island.

Graphic: None

 

AFE No. S-55-26

Sta or MP: Various, Minn

Division: Minnesota

Work Begun: Oct 20, 1925

Project Completed: Dec 1, 1925

Description of Project: Equipped section tool houses with storage bins and shelving per std plan 16994.  At Glenwood East, Glenwood West, Lowry, Farwell, Kensington, Hoffman, Barrett, Elbow Lake, Wendell, Nashua, and Tenney.

Graphic: None

 

AFE No. S-56-26

Sta or MP: Various, Minn

Division: Winnipeg

Work Begun: Sep 2, 1925

Project Completed: Jan 18, 1926

Description of Project: Equipped section tool houses with storage bins and shelving per std plan 16994. At Winger, Erskine, Cisco, Brooks, Plummer, Hazel, Thief River Falls (3), Anita, Newfolden, Strandquist, Karlstad, Halma, Bronson, Lancaster, Orleans, and Sultan.

Graphic: None

 

AFE No. S-57-26

Sta or MP: Various, Minn

Division: TC Term

Work Begun: Nov 18, 1925

Project Completed: Nov 25, 1925

Description of Project: Equipped section tool houses with storage bins and shelving per std plan 16994.  At Markville, Cloverton, Kingsdale, Belden, and Harlis.

Graphic: None

 

AFE No. S-58-26

Sta or MP: Daleview and Whitetail, Mont

Division: Minnesota

Work Begun: Apr 5, 1926

Project Completed: Apr 6, 1926

Description of Project: Installation of telegraphones at Daleview and Whitetail for telephone communications between those towns.  Ret S-626-43.

Graphic: None

 

AFE No. S-59-26

Sta or MP: Spur D-124, Minn

Division: TC Term

Work Begun: Nov 30, 1925

Project Completed: Dec 1, 1925

Description of Project: Construction of a 508 ft extension to the present 700 ft spur serving C R Grace 3 miles north of Belden, known as Spur D-124.  Orig spur constructed under S-823-25

Graphic: Map

 

AFE No. S-60-26

Sta or MP: Various, Mich

Division: Gdstn

Work Begun: Apr 1926

Project Completed: Nov 1926

Description of Project: Renewed or retired 9 culverts between MP 431 and MP 484.

Graphic: None

 

AFE No. S-61-26

Sta or MP: Various, Mich

Division: Gdstn

Work Begun: Apr 21, 1926

Project Completed: Jul 30, 1926

Description of Project: Renewed 5 culverts between MP 365 and MP 391.

Graphic: None

 

AFE No. S-62-26

Sta or MP: Various, Mich

Division: Gdstn

Work Begun: Jun 16, 1926

Project Completed: Jun 18, 1926

Description of Project: Renewed or abandoned 3 culverts between MP 327 – MP 339.

Graphic: None

 

AFE No. S-63-26

Sta or MP: Various, Wis

Division: Gdstn

Work Begun: Mar 19, 1926

Project Completed: Nov 27, 1926

Description of Project: Renew or abandon 42 culverts on W&N line between MP 245 and MP 339.

Graphic: None

 

AFE No. S-64-26

Sta or MP: Various, Wis

Division: Gdstn

Work Begun: Apr 1926

Project Completed: Nov 1926

Description of Project: Renew 4 culverts between MP 230 and MP 279.

Graphic: None

 

AFE No. S-65-26

Sta or MP: Various, Wis

Division: Gdstn

Work Begun: Apr 1926

Project Completed: Jul 7, 1926

Description of Project: Renew Culver 142-1/8-P and retire culvert 120-P.

Graphic: None

 

AFE No. S-66-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Jul 16, 1926

Project Completed: Jul 20, 1926

Description of Project: Renew old worn out timber box culverts A-121-Q and

A-132-Q.

Graphic: None

 

AFE No. S-67-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Apr 1926

Project Completed: Nov 19, 1926

Description of Project: Installed new culvert B-97-1/2 under main and house track at Hillsdale and renewed culvert B-104-P with concrete pipe.

Graphic: None

 

AFE No. S-68-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Apr 3, 1926

Project Completed: Nov 1, 1926

Description of Project: Renewed worn out timber box and vitrified culverts with reinforced concrete pipe, culverts 54-Q-1/8 , 68-P , and 75-Q 

Graphic: None

 

AFE No. S-69-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Mar 16, 1926

Project Completed: Aug 28, 1926

Description of Project: Renewed culverts D-131-P , D-131-T , and D-133-P with concrete pie and constructed wing wall at culvert D-133-P 

Graphic: None

 

AFE No. S-70-26

Sta or MP: Various, Minn

Division: TC Term

Work Begun: Mar 16, 1926

Project Completed: Sep 1, 1926

Description of Project: Renewed old worn out timber box culverts with reinforced concrete pipe at culverts D-128-S and D-128-T

Graphic: None

 

AFE No. S-71-26

Sta or MP: Various, Wis

Division: TC Term

Work Begun: Mar 12, 1926

Project Completed: Jul 28, 1926

Description of Project: Renewed old worn out culverts, 7 on Dresser Line between

MP D-65 and MP D-92.

Graphic: None

 

AFE No. S-72-26

Sta or MP: Various, Minn

Division: Minnesota

Work Begun: Mar 1926

Project Completed: Nov 20, 1926

Description of Project: Renewed old worn out timber box culverts under track and highway at culverts 15-2/8-P, 24-Q, 28-Q, and 36-Q-2/8

Graphic: None

 

AFE No. S-73-26

Sta or MP: Dent, Minn

Division: Winnipeg

Work Begun: Jun 30, 1926

Project Completed: Jul 1, 1926

Description of Project: Move highway grade crossing 8’ east to conform to change in relocation of road on north side of track and to clear up view of trains. Old crossing 874+52 and new crossing at 874+60.

Graphic: Map

 

AFE No. S-74-26

Sta or MP: Manistique, Mich

Division: Gdstn

Work Begun: Nov 9, 1925

Project Completed: Nov 13, 1925

Description of Project: Construction of a 440’ track to serve Manistique Lime and Stone Co.  HB of new track located in shifted coal track 111’ from HB of coal track.  Also shifted coal track.  New track all off ROW.

Graphic: Map

 

AFE No. S-75-26

Sta or MP: Navarino, Wis

Division: Gdstn

Work Begun: Dec 12, 1925

Project Completed: Dec 12, 1925

Description of Project: Construction of 224 LF of 5 board permanent snow fence on present 2 BW and 36” WW fence 112 ft on each side of ROW to project east house track switch at Navarino.  sta 690+18 to 691+36.

Graphic: Map

 

AFE No. S-76-26

Sta or MP: Various, ND

Division: Mo River

Work Begun: Apr 26, 1926

Project Completed: Nov 24, 1926

Description of Project: Renew, demolish, and install 24 culverts located between MP 443 and MP 524 on Drake-Sanish Line.

Graphic: None

 

AFE No. S-77-26

Sta or MP: Culvert X-510-Q , ND

Division: Mo River

Work Begun: Apr 14, 1926

Project Completed: Apr 14, 1926

Description of Project: Renewal of Culvert X-510-Q with concrete p